Ascometal Fos-sur-Mer
The decision to build the Ugine-Aciers stainless steel plant west of Marseille was taken in 1971. The plant was originally built as "Steelworks B" of the giant SOLLAC-Solmer (now ArcelorMittal Fos-sur-Mer) integrated plant in the immediate vicinity.
The first tapping of the 100 t U.H.P electric arc furnace took place in 1973. The cast ingots are further processed at the bar rolling mill and the wire mill.